This month marked a major milestone for the geothermal energy system project with the last well being drilled in lot 36 on October 18th. Paving was completed in Lot 8 and put in service early last week for
parking and the schedule of the well drilling and parking lot
replacement continues to track well. Circuit piping in lot 36 will continue until its completion date of mid-November. Additionally, it appears lot 36 is ahead of schedule and will be back in service near the end of December (weather permitting). Lot 11 remains on schedule to be back in service by the third week of November.
Our primary goals for the next two months is to complete all geothermal piping and have both parking lots 11 and 36 back in service before winter.