Temporary Access to Computer Science Building

Due to geothermal construction & weather conditions, see below the temporary access path to Computer Science Building and access to South campus from North parking lots. Thank you for your continued patience as we transition to a greener campus.

Entrance Map

Missouri S&T Geothermal Energy System Featured on KY3 Today

The geothermal energy system was featured on KY3 this morning. To see the video, go here. … [Continue reading]

Frequently Asked Questions

Diagram

We've had several questions asked regarding the geothermal energy system, so here are a few answers to those questions. We'll post a few more on our blog as we receive more questions. How many wells are there? What is the average, maximum, and … [Continue reading]

Alternate Routes from Lot M36 and M19

M-36 Route Map

Due to construction on the geothermal energy project, alternate routes may have to be taken to buildings from parking lots M19 and M36. Please see the following map below for alternate routes. We appreciate your patience during this period as we … [Continue reading]

Trenching Continues

Geothermal Progress-010

The geothermal project is moving along well, although construction has experienced some delays due the rainy spring weather. Over the past weeks, trenching has largely been focused on the northwest mall area. As progress continues, trenching will … [Continue reading]

Lot 11 Opening Postponed

Lot 11 construction has been delayed, but will be opened by December 21. Please contact Design & Construction Management with any questions at 341-4252. … [Continue reading]

Geothermal Well Drilling Complete

This month marked a major milestone for the geothermal energy system project with the last well being drilled in lot 36 on October 18th. Paving was completed in Lot 8 and put in service early last week for parking and the schedule of the well … [Continue reading]

North Lots Complete

geo-lot

Overall, the well drilling and geothermal header project continues to progress well. Well drilling exceeds 60% completion for the project, the north street crossings have been completed and circuit and header piping back to the Straumanis Plant is … [Continue reading]

Progress Continues With Drilling and Piping

Geothermal%20Drilling-8599-thumb-800x533-27083

Well drilling has continued at a rapid pace with Durbin Geothermal keeping more than four drill rigs on site. Focus has now been directed to the circuit piping in the well fields and header piping back to the geothermal plants to allow the northeast … [Continue reading]

Geothermal Well Drilling Continues

schedule-06-22-12

As geothermal well drilling continues, additional parking spaces are being be displaced. Area C Lot 11 (across 10th Street from Castleman Hall) is scheduled to close at the beginning of July and will be closed until approximately December 2012. Area … [Continue reading]